Current Projects

38 Blackshaws Road
South Kingsville 3015

View LTE Works

LTE Construction Group have been contracted to complete the bulk earthworks for Newport Village: stockpiling to multiple locations and material conditioning for earthworks.

37-63 Bell Street
Ivanhoe 3079

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, anchors, capping beam and shotcrete walls.

144-160 Keilor Road
North Essendon 3041

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, anchors, capping beam, shotcrete walls, crane base and detailed excavation.

685 La Trobe Street
Docklands 3008

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, foundation piles, anchors, capping beam and shotcrete walls.

12-22 Wellington Road
Box Hill 3128

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, anchors, capping beam and shotcrete walls.

663 Malvern Road
Toorak 3142

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, anchors, capping beam and shotcrete walls.

Knox Redevelopment Project
Wantirna South 3152

View LTE Works

LTE Group have been contracted to complete piling works.

18-24 Hopkins Street
Footscray 3011

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, anchors, capping beam and shotcrete walls.

21-23 William Street
Balaclava 3183

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, anchors, capping beam and shotcrete walls.

153 Sturt Street
Southbank 3006

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, anchors, capping beam and shotcrete walls.

550 Spencer Street
West Melbourne 3003

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, anchors, capping beam and shotcrete walls.

West Gate Tunnel Project
Yarraville 3013

View LTE Works

The West Gate Tunnel will give Melbourne new links to the port, CityLink and Melbourne CBD.

LTE Construction Group have constructed nearly 1000 bored piles for bridge foundations, noise walls and other structures all socketing into hard basalt. This includes occupation works for bridge piles at the M80 interchange, night shift and weekend works as required by the project to meet program requirements.

249-265 Queens Pde
Fitzroy North 3068

View LTE Works

LTE Group have been contracted to complete the following: bulk excavation works, retention piles, anchors, capping beam and shotcrete walls.